Pool Screen Cage Replacement (Project #4672) – Via D Arezzo Dr, Bonita Springs, FL

Screen Pool Enclosure
map_check_alt Bonita Springs
calendar_alt September 10, 2026
size_alt 1,347 sq. ft. footprint; 3,000 sq. ft. structure area; up to 15.5 ft high
Super Screen Roof
No-See-Um Walls
Concrete Footing
Bronze Frame

This Bonita Springs project replaced an old pool cage with a new bronze pool screen cage over the pool, the raised spa, and the paver deck. It covers 1,347 sq. ft., rises to about 15.5 ft, and stands on a new concrete footing. Super Screen 17/20 covers the roof and No-See-Um 20/20 the walls. It was completed on September 10, 2026.

Project Value: Around $25,000
Pool screen cage after project Bonita Springs 4672
Pool screen cage corner view with pool and spa Bonita Springs 4672
Pool screen cage exterior view with palm tree Bonita Springs 4672
Pool screen cage long side view from the yard Bonita Springs 4672
Pool screen cage pool and screen roof from the lanai Bonita Springs 4672
Pool screen cage screened side walkway along the house Bonita Springs 4672
Pool screen cage side entry door and screen door Bonita Springs 4672
Pool screen cage open pool deck after old cage removal Bonita Springs 4672
Pool screen cage after project Bonita Springs 4672
Pool screen cage corner view with pool and spa Bonita Springs 4672
Pool screen cage exterior view with palm tree Bonita Springs 4672
Pool screen cage long side view from the yard Bonita Springs 4672
Pool screen cage pool and screen roof from the lanai Bonita Springs 4672
Pool screen cage screened side walkway along the house Bonita Springs 4672
Pool screen cage side entry door and screen door Bonita Springs 4672
Pool screen cage open pool deck after old cage removal Bonita Springs 4672
01
/
01

Project Overview

At a home on Via D Arezzo Dr in Bonita Springs, the old screen cage over the pool had reached the end of its service life. Project #4672 removed it and built a new bronze pool screen cage over the pool, the raised spa, and the paver deck. The new cage covers a footprint of 1,347 sq. ft., its walls and roof add up to a structure area of 3,000 sq. ft., and it rises to about 15.5 ft.

A cage of this height and span needs a strong frame. The main members are 6-inch square aluminum tubes, and the roof is carried by SMB beams from 2 × 6 up to 2 × 10. Gusset plates stiffen the joints, cables with triangle brackets brace the walls, and the frame is fastened with stainless steel screws and anchors. Along the side of the house, the cage continues as a screened walkway.

Two meshes share the work. The roof panels use Super Screen 17/20, a heavier mesh made for large spans overhead, and the side panels use No-See-Um 20/20, a fine weave that stops very small biting insects at eye level. A 7-inch Super Gutter with a 3 × 4 downpipe carries the roof water, and a screen door with an 8-inch kick plate opens to the yard.

Before the frame went up, the crew built a new concrete footing along the edge of the paver deck. Every property needs its own measurements and estimate, so the figures here describe this installation only.

Homeowners considering a similar upgrade can explore our screen pool enclosures in nearby Estero.

Permit review for a project like this typically takes about 2 weeks. The footing was built in mid-August, the old cage was removed on August 18, and installation of the new cage ran from September 3 to September 10, 2026. The work was reported at a cost of around $25,000.

Before & After

Before
After
Pool screen cage before project Bonita Springs 4672
Pool screen cage after project Bonita Springs 4672

New Concrete Footing for This Bonita Springs Pool Cage

A pool cage this tall needs a solid base along its walls. Before the new frame went up, our crew dug a trench along the edge of the paver deck, lifted the pavers next to it, and set wooden forms to shape the new concrete footing.

The footing was built on August 13 to 15, 2026, while the old cage was still standing, so the pool area stayed usable as long as possible. The footing gives the posts of the new cage a continuous concrete base instead of resting on the pavers.

Once the concrete had set, the pavers along the edge were relaid against the footing, and the deck was ready for the new frame. The finished surface looks like the original paver deck, with the new base hidden underneath.

How We Did It

Project #4672 followed the complete design-build sequence for replacing a pool screen cage in Bonita Springs. After an on-site consultation and measurements, the team confirmed the layout of the new cage, its two meshes, and the footing. The drawings and the permit came next. The footing was built in mid-August, the old cage was removed on August 18, and installation of the new cage took 8 days, from September 3 to September 10, 2026, before the cage moved into warranty and ongoing company support.

01
On-Site Consultation, Measurements & Contract

Our specialist visited the Bonita Springs property to evaluate the old cage, the pool and spa, the paver deck, the house wall, the roofline, and the yard around them. Measurements were taken for the new cage, including the section along the side of the house. During this stage, the homeowners selected the bronze finish, Super Screen for the roof, No-See-Um mesh for the walls, and one screen door. After the scope, materials, pricing, and timeline were confirmed, the contract was finalized.

On-Site Consultation, Measurements & Contract
02
3D Visualization & Engineering Design

Using the field measurements, the team prepared the drawings for the new cage: the footprint and height, the 6-inch square tube members and SMB roof beams, the gusset plates and cable bracing, the concrete footing along the deck, the gutter with its downpipe, and the position of the screen door. This planning stage fixed how each member is sized and connected.

3D Visualization & Engineering Design
03
Permit Application & Approval

Once the drawings were complete, the permit package was prepared and submitted for review. For a cage of this size, permit review typically takes about 2 weeks in our projects. Review periods differ by property and by county, so another project may need a different timeline.

Permit Application & Approval
04
Material Preparation & Pool Enclosure Installation

The new concrete footing was built along the paver deck on August 13 to 15, 2026, and the old cage was removed on August 18. Installation of the new cage started on September 3. The installers set the 6-inch square tube members and the SMB roof beams with gusset plates, added the cable bracing, and connected the 7-inch Super Gutter and downpipe. Super Screen was fitted to the roof, No-See-Um mesh to the walls, and the screen door was installed. Installation took 8 days.

Material Preparation & Pool Enclosure Installation
05
Final Inspection & Client Handover

After installation, the team checked the screen tension on the roof and walls, the cable bracing, the frame connections, the gutter, the door operation, and the overall finish. The completed cage covers the pool, the raised spa, and the paver deck, and continues along the side of the house. Project #4672 was completed on September 10, 2026, and the cage was ready for everyday use.

Final Inspection & Client Handover
06
Warranty & Ongoing Project Support

Following the final handover, the new pool screen cage was placed under Screen Factory Florida’s warranty and ongoing support. Our team remains available to assist with questions related to the Super Screen roof, the No-See-Um walls, the bronze frame, the Super Gutter, the cable bracing, the screen door, or other installed components. The homeowners can now enjoy a protected pool area with dependable support after installation.

Warranty & Ongoing Project Support

Want a Similar Result?

Get a free estimate for your project —
we’ll call you back within 15 minutes.

Design, Permits & Project Planning

Project #4672 replaced an old pool cage at a home on Via D Arezzo Dr in Bonita Springs with a new bronze pool screen cage. The cage covers 1,347 sq. ft., rises to about 15.5 ft, and continues along the side of the house. Planning covered the concrete footing along the paver deck, the 6-inch square tube members and SMB roof beams, the cable bracing, the 7-inch Super Gutter, and two meshes: Super Screen on the roof and No-See-Um on the walls. The project was completed on September 10, 2026.

Pool Screen Cage
Pool Cage Replacement
Super Screen Roof
Bonita Springs Pool Cage
Concrete Footing
Built Right. Approved. Protected.

We engineer every enclosure to meet the strict 8th Edition Florida Building Code (2023), designed to meet applicable Florida Building Code structural and wind-load requirements.

Frequently Asked Questions

Answers to common questions about replacing a pool screen cage in Bonita Springs, including cost, footings, meshes, permits, and timelines.

How much does it cost to replace a pool screen cage in Florida?

The cost depends on the size and height of the cage, the roof design, the frame members, the meshes, the doors, the removal of the old cage, and any concrete work. Tall cages need larger beams and bracing, and a new footing adds to the scope. For Project #4672 in Bonita Springs, the reported cost was around $25,000 for a new bronze cage with a 1,347 sq. ft. footprint, a height of about 15.5 ft, a new concrete footing, Super Screen on the roof, and No-See-Um mesh on the walls. That figure describes this installation only. The most reliable way to price your own cage is an on-site visit and a written estimate.

Why use different screen mesh on the roof and the walls?

The roof and the walls do different jobs. The roof panels span farther and collect leaves and debris, so a heavier mesh such as Super Screen 17/20 holds its shape better overhead. The walls are at eye level, where small biting insects get in, so a fine No-See-Um 20/20 weave works well there. On Project #4672, the roof uses Super Screen and the walls use No-See-Um mesh. Heavier mesh lets slightly less light through, so ask your contractor to show samples of both and explain how each affects the view, the airflow, and the expected service life. On a tall cage, the choice of roof mesh also affects how much debris collects overhead and how often the roof needs a rinse.

Does a new pool cage need a concrete footing?

Often, yes. The posts of a pool cage carry wind and roof loads, and a concrete footing gives them a continuous base instead of resting on pavers. Whether a new footing is needed depends on the height of the cage, the existing slab or deck, and the engineering for the project. On Project #4672 in Bonita Springs, the crew dug a trench along the paver deck, formed and poured a new concrete footing, and relaid the pavers before the new cage went up. Ask your contractor to show the footing on the drawings and to explain how the posts connect to it. Without a proper base, posts on pavers can shift over time as the pavers settle.

How long does it take to replace a pool screen cage?

The timeline has several parts: the permit stage, the footing, removal of the old cage, and installation of the new frame and screen. On Project #4672 in Bonita Springs, the footing was built on August 13 to 15, 2026, the old cage was removed on August 18, and installation of the new cage took 8 days, from September 3 to September 10, 2026. Permit review for a project like this typically takes about 2 weeks. A larger or taller cage, or a cage with a long side section, can take longer, and weather can move the dates. Ask for the schedule in writing before you sign a contract, and ask who submits the permit and schedules the inspections.

Do you need a permit to replace a pool cage in Bonita Springs?

In most cases, yes. A pool screen cage is a permanent structure, and replacing it is usually reviewed by the local building department before construction, including the footing and the frame. Bonita Springs is in Lee County, so check with the city or county building department or ask your contractor to confirm the requirements for your address. In our projects, permit review for a cage like this typically takes about 2 weeks, but another project may take more or less time. A contractor who prepares the drawings and submits the application can keep the schedule clear, and the permit card stays on site during the work.

More projects

Explore more screen enclosure and pool cage projects in the Florida area.

Our Services

From custom pool enclosures and screened lanais to motorized screens and hurricane shutters, we create outdoor spaces made for the Florida lifestyle. Every solution combines lasting protection, everyday comfort, and clean design – so you can enjoy more fresh air, fewer insects, and peace of mind in any weather.

form-user-alt
Alex Martin
Senior Project Consultant, Screen Factory Florida
greetings-img Hi, I'm Alex, your project consultant. Fill in the details and I'll personally get back to you today.
Whether you need a free estimate or have questions about your project, just fill out the form - I'll personally get back to you today.
Name
Error
Phone
Error
Email
Error
Service Needed
Error
City
Error
Zip
Error
Address (Optional)
Error
Message (optional)
0/1000
Error
I have read and agree to the Privacy Policy and Terms of Service.